Automatic 5L Barrel Pure Water Filling Machine Washing Filling Capping Line
Summary:
(1) This Mineral Water Bottling Plant is mainly used for washing, filling and capping PET bottle which can fill non- carbonated drinks such as mineral water, pure water, wine and so on. from 3L-10L
(2) Bottle washing, filling and capping are achieved in one machine.
(3) The contact time is shorten between material and the outside. And improved the health conditions, production capacity and economic benefits.
(4) CGF series Mineral Water Bottling Plant adopts hanging type conveying-bottle structure to make changing bottle mold more convenient, faster and more laborsaving.
(5) The main machine adopts advanced PLC control technology. The key electric elements adopt Mitsubishi, Omron, Siemens, etc international famous products.
Whole machine power:
★ main motor: 2.2KW
★ spraying pump: 0.55KW
★ liquid feedback pump: 0.55KW
★ water consumption: 1.5t/h
★ overall size: 2400*1850*2400mm
★ weight: 3600Kg
Electricity list
1 PRICE: FOB Shanghai
Note: Price period of validity: 180 days
2. PAYMENT
30% deposit against the contract by T/T should be paid before the order;
70% balance should be paid off by T/T after inspection before delivery;
3. DELIVERY TIME
30 working days after the down payment;
4. TRAINNING
The Buyer could dispatch their operators to the Seller's factory for training, including machine operation, maintenance & simple repairs;
Or against the requests of the Buyer, the Seller's technician could train the Buyer's operators in the Buyer's factory in the periods of installing & adjusting; the training is free of charge;
5. INSTALLATION & ADJUSTMENT
The Seller could dispatch an engineer against the requests of the Buyer to install and adjust the machines for one week in the Buyer's factor
y.
The Buyer should make a reservation in advance before delivery of the machines;
The Buyer should pay for the engineer's visa application cost, round air tickets, food & board before his departure; And pay USD 80/day to engineer.
6. GUARANTEE
The guarantee time is one year after the machines normally works in the Buyer's factory, if only the problem is cause due to quality control or any reason by the Seller. We will supply replaced parts free of charge and our engineers will guide you how to solve the problems.
Any problems caused due to irregular operation or incorrect maintenance by the Buyer won't be listed in guarantee coverage.
washer-filler-capper details photos
Some client bottle samples:
After sale service
1. Welcome to consult us for offer and technical solution:
2. free design workshop layout as workshop space.
3. free check raw material quality report to match suit water treatment system.
4. Engineer install and train client how to use and maintain machine
5. one year guarantee
6. if some client urgently need machine, we can ship machine half month under supply caps and bottle samples to meet with client quick need.
Some basic details need buyer support:
1. bottle and cap samples
2. workshop space length and width size
3. source water quality report
4. capacity requirement, we will match solution as it. we have capacity from 1000bph to 24000bph
5. and other details need check
View more product, you can click product keywords...